Watch out for that hole
Excavation began on Tuesday. I haven't been out of the house since ![]()
Monday- thank you Influenza. Stuart has been sending photos of the progress, but I didn't understand the magnitude until I walked over there today. WOW!
The basement needed to be 10'6", then an additional 11" for the footing. The excavation also needed to be about 5' outside of the actual walls. Add that up and we are digging close to the property lines, hence the Shoring. So I asked,"How many yards of dirt have they taken away?". Care to guess? About 550 yards. If you have ever done any landscaping, one or two yards seems enough soil to make your back ache, but 550. Geese. The dirt dance is trying to figure out how much dirt to keep on property to allow for back fill and how much to send away. We have yet to see how we weigh in there, but I'll trust Rick (having dug a few hundred basements).
![]()